Environmental Litigation

Hermosa Critical Minerals Project: Court Denies Injunction Bid

Hermosa Critical Minerals Project ruling: a federal court in Arizona denied a preliminary injunction, letting approved construction proceed in November 2026.

Advertisement

Advertisement

Photograph of an industrial site and waterway under overcast light, illustrating Hermosa Critical Minerals Project: Court Denies Injunction Bid.
Photograph of an industrial site and waterway under overcast light, illustrating Hermosa Critical Minerals Project: Court Denies Injunction Bid.
On this page

Something in this article wrong, out of date, or missing its source? Tell the editorial desk.

The U.S. District Court for the District of Arizona denied a motion for a preliminary injunction that would have halted construction of the Hermosa Critical Minerals Project in southeastern Arizona, the Department of Justice announced on November 10, 2026. The court found that the plaintiffs had not shown a likelihood of success on their claims. The court also found that the plaintiffs had not made the required showing of likely irreparable harm. Approved work on the project can proceed while the court considers the merits on an expedited schedule.

At a glance

Card listing the primary documents cited in “Hermosa Critical Minerals Project: Court Denies Injunction Bid”, with the publisher of each
The primary documents this article cites, by publisher. Each is linked in full under Sources.
  • The U.S. District Court for the District of Arizona denied the preliminary injunction motion in the week before November 10, 2026; the Department of Justice release, Press Release Number 26-1339, describes the decision as issued “last week.”
  • The U.S. Forest Service approved the Hermosa Critical Minerals Project in July 2026, after roughly three years of environmental review.
  • The approval imposes more than 400 binding design features, mitigation measures and other conditions, and followed formal consultation with the U.S. Fish and Wildlife Service under the Endangered Species Act.
  • The Department of War awarded the project $20 million under the Defense Production Act, and the Department of Energy awarded $166.2 million.
  • Two environmental groups challenged the agencies’ decisions in late October 2026; the release does not name them.

What the Arizona federal court decided

A preliminary injunction is an interim order that can pause a project while a lawsuit proceeds; it is not a ruling on the merits of the claims. The U.S. District Court for the District of Arizona denied that request, so approved work on the Hermosa Critical Minerals Project is not barred from continuing.

The Department of Justice release gives three reasons for the denial. First, the plaintiffs had not shown they were likely to succeed on their claims. Second, the plaintiffs had not made the required showing of likely irreparable harm. Third, the court recognized “a substantial public interest in domestic critical-mineral supply” and noted that “the national security interests are relevant and substantial.”

What the project involves and what agencies approved

The Department of Justice describes the Hermosa Critical Minerals Project as establishing a domestic source of manganese and substantially increasing domestic production of zinc. The release states that both metals are essential to the steel used in military vehicles and naval vessels, and that battery-grade manganese is essential to the lithium-ion batteries that power unmanned aerial vehicles, radios and other defense equipment. It also states that the United States relies entirely on imports of manganese and almost entirely on imports of zinc, with China providing about 95% of global refining capacity for manganese used in advanced batteries.

The U.S. Forest Service approved the project in July 2026. The project expands existing mining operations on private land onto the Coronado National Forest. The approval followed formal consultation with the U.S. Fish and Wildlife Service under the Endangered Species Act and imposes more than 400 binding design features, mitigation measures and other conditions to minimize environmental impacts.

The release further states that the Department of War awarded the project $20 million under the Defense Production Act and that the Department of Energy awarded $166.2 million, to accelerate manganese and zinc production and refining. Principal Deputy Assistant Attorney General Adam Gustafson of the Justice Department’s Energy and Natural Resources Division (ENRD), the division that defends federal agency actions in environmental litigation, said in the release that “manganese is indispensable to our national defense.”

What is established vs. what is alleged

Established in the record: the U.S. District Court for the District of Arizona denied the preliminary injunction motion, the U.S. Forest Service approved the project in July 2026, the two funding awards were made, and two environmental groups filed a challenge in late October 2026.

Alleged: the environmental groups’ claims against the agencies’ decisions. The denial of a preliminary injunction does not resolve those claims. The release reports only that the plaintiffs had not shown a likelihood of success at this stage, and it does not describe the statutes or theories they raised beyond the Endangered Species Act consultation that preceded the Forest Service approval.

Where the claims stand procedurally

The challenge is pending in the U.S. District Court for the District of Arizona, which the release says is considering the merits on an expedited schedule. The release does not provide a docket number, a trial date, or a ruling date beyond “last week,” and it does not say whether any appeal has been filed.

The documents supplied show no multi-district litigation, the federal procedure that consolidates related cases from different districts before one judge, and no MDL number appears in them. Attorneys with ENRD’s Wildlife and Marine Resources Section and Natural Resources Section are handling the matter for the government, according to the release. Comparable ENRD defense work appears in the division’s announcements on the Army Corps Clean Water Act permit for the Cainhoy Plantation development and the Navy’s fuel release response at Joint Base Pearl Harbor-Hickam.

Key dates

  • July 2026: The U.S. Forest Service approved the Hermosa Critical Minerals Project after roughly three years of environmental review.
  • Late October 2026: Two environmental groups challenged the agencies’ decisions and asked the court to halt the project while the case proceeds.
  • Week before November 10, 2026: The U.S. District Court for the District of Arizona denied the preliminary injunction motion.
  • November 10, 2026: The Department of Justice’s Office of Public Affairs published Press Release Number 26-1339 announcing the denial.

What this does not establish

  • The record does not show that any court has ruled on the merits of the environmental groups’ claims.
  • The release does not identify the plaintiffs, the presiding judge or a docket number.
  • The release does not give the exact date of the ruling, describing it only as “last week.”
  • The release does not state whether the plaintiffs have appealed or intend to.
  • The release does not state whether construction has begun or how much work has been completed.
  • Statements about import dependence, national security and project benefits are the Department of Justice’s characterizations; the court language quoted is limited to the passages reproduced in the release.

Frequently asked questions

Did a federal court halt the Hermosa Critical Minerals Project?

No. The U.S. District Court for the District of Arizona denied a motion for a preliminary injunction that would have halted construction of the Hermosa Critical Minerals Project. The Department of Justice announced the denial in a press release dated November 10, 2026. Approved work can proceed while the court considers the merits on an expedited schedule.

Why did the court deny the preliminary injunction?

The U.S. District Court for the District of Arizona denied the motion because the plaintiffs had not shown they were likely to succeed on their claims, according to the Department of Justice release. The court also found that the plaintiffs had not made the required showing of likely irreparable harm. The court further recognized a substantial public interest in domestic critical-mineral supply and described the national security interests as relevant and substantial.

Which groups challenged the Hermosa project?

The Department of Justice release refers to two environmental groups that challenged the agencies’ decisions in late October 2026, and it does not name them. The release likewise does not identify individual plaintiffs or their counsel.

What federal review came before the lawsuit?

The U.S. Forest Service approved the Hermosa Critical Minerals Project in July 2026 after roughly three years of environmental review. The approval followed formal consultation with the U.S. Fish and Wildlife Service under the Endangered Species Act. It also imposes more than 400 binding design features, mitigation measures and other conditions.

Is the Hermosa dispute part of an MDL?

The documents supplied do not show any multi-district litigation or MDL number for the Hermosa dispute. An MDL consolidates related federal cases from different districts before one judge. The challenge described in the Department of Justice release is a single case before the U.S. District Court for the District of Arizona.

Sources

  1. U.S. Department of Justice, Office of Public Affairs: “Arizona Federal Court Denies Request to Halt Hermosa Critical Minerals Project” (link, accessed 2026-11-12)
  2. U.S. Department of Justice, Energy and Natural Resources Division: “News” (link, accessed 2026-11-12)
  3. U.S. Department of Justice, Energy and Natural Resources Division: “Learn More about the Division” (link, accessed 2026-11-12)
  4. U.S. Department of Justice, Energy and Natural Resources Division: “Energy and Natural Resources Division” (link, accessed 2026-11-12)
  5. U.S. Department of Justice, Energy and Natural Resources Division: “Find Help” (link, accessed 2026-11-12)

Related coverage

CollectiveClaim.us publishes general legal information. This article is not legal advice and does not create an attorney–client relationship. Court records and agency actions change; verify current status with the court or agency before relying on it.